What is the difference between a time-and-materials and lump-sum change order?

Direct Answer

A lump-sum change order establishes one agreed price for a clearly defined change in the work, while a time-and-materials (T&M) change order pays the contractor based on actual labor, materials, equipment, and other contractually allowable costs incurred.

The key difference is who carries the risk that the actual cost will differ from the estimate. With lump-sum pricing, the contractor generally carries more cost risk after agreeing to the fixed amount. With T&M pricing, the owner generally carries more quantity and cost risk because the final amount depends on the actual resources used.

Construction-industry guidance recognizes both methods as common ways to price change orders. Lump-sum pricing works best when the scope and quantities can be reasonably established before the work begins. T&M pricing is more appropriate when the extent or duration of the work cannot be estimated with reasonable confidence.

Who This Applies To

  • Commercial property owners
  • General contractors
  • Commercial roofing contractors
  • Property and facility managers
  • Developers and owners’ representatives
  • Construction project managers
  • Architects and consultants administering construction contracts

Not for: The exact pricing method, markup, documentation requirements, authorization procedure, and payment rules depend on the underlying construction contract and applicable change-order provisions.

1. What Is a Lump-Sum Change Order?

A lump-sum change order establishes a fixed amount for a defined change in the contract work.

For example, suppose a commercial roofing project requires an additional 4,000 square feet of membrane replacement and the quantities, materials, labor requirements, and access conditions can all be reasonably determined. The contractor may submit a change order for one agreed price covering the defined additional work.

Once properly executed, the agreed price generally does not change simply because the contractor’s actual cost turns out to be higher or lower than anticipated, subject to the terms and conditions of the contract.

Industry guidance describes lump-sum changes as particularly useful when the contractor can estimate the complete cost of the change before the work begins.

2. What Is a Time-and-Materials Change Order?

A time-and-materials change order calculates payment from the actual resources used to perform the additional work, using rates and markups established by the contract or change order.

Depending on the agreement, this can include:

  • Actual labor hours
  • Agreed labor rates
  • Materials actually incorporated into the work
  • Equipment usage
  • Subcontractor costs
  • Approved delivery or other direct costs
  • Contractually permitted overhead and profit

Federal acquisition regulations describe T&M pricing as payment based on specified labor rates plus actual material costs, rather than a fixed price. Construction contracts may establish different T&M documentation and markup requirements, so the governing contract should always be checked.

3. The Main Difference Is Cost Certainty

Factor Lump-Sum Change Order Time-and-Materials Change Order
Price Fixed agreed amount Based on actual allowable costs
Scope Usually clearly defined May be uncertain or evolving
Owner cost certainty Higher Lower unless capped
Contractor cost risk Generally higher Generally lower
Documentation Cost breakdown and scope support Detailed labor, material, equipment and cost tracking
Best suited for Known quantities and defined work Unknown conditions or difficult-to-quantify work

The Los Angeles Bureau of Engineering similarly distinguishes finalized lump-sum change orders from final T&M change orders, with T&M work requiring documentation of the final scope, cost, and schedule impacts.

4. When Should a Commercial Roofing Change Order Be Lump Sum?

Lump-sum pricing is generally preferable when the contractor can accurately establish the scope before beginning the additional work.

Examples include:

  • Adding a defined area of membrane
  • Replacing a known quantity of flashing
  • Installing a specified number of roof drains
  • Replacing a clearly identified section of damaged insulation
  • Adding a defined number of roof accessories
  • Performing a clearly quantified repair

If the contractor can perform a reliable takeoff and identify the materials, labor, equipment, access requirements, and other relevant costs, a fixed price can give the owner better budget certainty.

5. When Is Time-and-Materials More Appropriate?

T&M is useful when the actual scope cannot reasonably be established until the work is opened up or investigated.

Commercial roofing examples include:

  • Emergency leak investigation
  • Concealed wet insulation
  • Unknown deck deterioration
  • Hidden structural damage
  • Storm damage whose extent has not yet been determined
  • Exploratory demolition
  • Repairs where the extent becomes visible only after membrane removal

For example, a contractor may open a roof assembly expecting a localized repair and discover additional concealed deterioration. A T&M structure can allow the investigation and corrective work to continue while the actual quantities are documented.

Industry guidance specifically identifies uncertain scope and quantities as circumstances where T&M pricing can be appropriate.

6. Who Carries the Cost Risk?

This is one of the most important differences.

With a lump-sum change order, the contractor estimates the cost in advance. If the contractor underestimated the labor or materials needed to complete the defined scope, the contractor may absorb the additional cost unless the contract provides another basis for adjustment.

With a T&M change order, the owner generally pays for the actual allowable resources used, subject to the agreed rates, markups, authorization procedures, and any contractual limits.

That means T&M provides flexibility but can create greater uncertainty for the owner’s final cost.

7. Can a T&M Change Order Have a Not-to-Exceed Amount?

Yes, if the parties agree to one.

A T&M change order can be structured with a not-to-exceed (NTE) amount, allowing the contractor to track actual costs while giving the owner a defined maximum unless additional authorization is obtained.

Some construction contract provisions expressly recognize T&M with a not-to-exceed amount as one method of determining a change-order adjustment.

An NTE limit should clearly state what happens if the contractor expects the work to exceed the authorized amount. Otherwise, the parties can end up disputing whether additional work was authorized.

8. What Documentation Is Needed for a Lump-Sum Change?

Even though the final price is fixed, the owner should require enough information to understand what is being purchased.

A good lump-sum change order should identify:

  • Description of the changed work
  • Reason for the change
  • Materials and quantities
  • Labor assumptions
  • Equipment requirements
  • Subcontractor quotations where applicable
  • Overhead and profit treatment
  • Schedule impact
  • Total change-order amount

Construction contract provisions commonly require supporting documentation for lump-sum change orders, including cost breakdowns and information sufficient to substantiate the proposed adjustment.

9. What Documentation Is Needed for T&M?

T&M requires stronger field-level cost tracking because the final amount depends on actual resources used.

Depending on the contract, documentation can include:

  • Daily labor hours
  • Employee classifications
  • Agreed labor rates
  • Material invoices
  • Equipment hours
  • Delivery tickets
  • Subcontractor invoices
  • Daily reports
  • Signed T&M tickets
  • Photographs
  • Daily descriptions of the work performed

Accurate tracking is particularly important because the owner needs to be able to verify that the amounts billed correspond to authorized change-order work. Industry guidance emphasizes accurate expenditure tracking for T&M changes.

10. What Happens if the Scope Changes During the Work?

If a lump-sum change order was based on a clearly defined scope and materially different conditions are discovered, the parties may need another change order or another contractual mechanism to address the additional work.

For example, a contractor receives a lump-sum change order to replace 500 square feet of damaged insulation. During removal, the contractor discovers that another 1,500 square feet is wet. The additional 1,500 square feet should not simply be added to the invoice without following the contract’s change-order procedure.

The parties should document the newly discovered condition, establish entitlement under the contract, and agree on the appropriate pricing method before proceeding when circumstances permit.

11. Which Method Is Better for the Owner?

Neither method is automatically better. The correct method depends on how well the scope can be defined.

Lump sum is generally better when:

  • The scope is known
  • Quantities can be measured
  • Materials are known
  • Access conditions are understood
  • The contractor can price the work reliably
  • The owner needs strong budget certainty

T&M is generally better when:

  • The scope is uncertain
  • Concealed conditions may exist
  • Emergency work is required
  • Investigation must occur before the final repair scope is known
  • Quantities cannot reasonably be established in advance

12. What Should Commercial Roofing Owners Watch For?

Owners should be especially careful when a contractor proposes T&M for work that appears readily quantifiable.

Before accepting T&M pricing, ask:

  • Why can the work not be priced as lump sum?
  • What is currently unknown?
  • What labor rates will apply?
  • What material markup will apply?
  • What equipment rates will apply?
  • What overhead and profit percentages apply?
  • Is there an NTE amount?
  • Who approves daily T&M tickets?
  • What happens when the NTE amount is reached?
  • What documentation must accompany the invoice?

These controls reduce the risk of disagreement about what work was authorized and how the final price was calculated.

13. Always Check the Original Contract

The change-order procedure should not be created from scratch each time. Review the original contract first.

Look for provisions addressing:

  • Change-order authorization
  • Pricing methods
  • Labor rates
  • Material markups
  • Equipment rates
  • Overhead and profit
  • Notice requirements
  • Daily T&M tickets
  • Not-to-exceed limits
  • Schedule extensions
  • Required signatures

A change order normally modifies the existing construction agreement, so the agreed pricing method should be consistent with the contract’s change-order provisions.

14. Put the Change in Writing Before the Work Proceeds When Possible

Written authorization is one of the most important protections for both parties.

The change order should clearly establish:

  1. What is changing
  2. Why the change is required
  3. How the change will be priced
  4. The authorized amount or pricing rates
  5. Any markup
  6. Any not-to-exceed amount
  7. Schedule impact
  8. Required documentation
  9. Who has authority to approve additional work

Public construction procedures commonly require the change order to document the agreed scope, cost, and schedule adjustments before it becomes the formal amendment to the contract.

15. Example: Commercial Roof Repair

Imagine a contractor is replacing a commercial roof section. During demolition, concealed deck deterioration is discovered.

Lump-sum approach: If the damaged deck area has been fully exposed and measured, the contractor can determine that 1,200 square feet needs replacement and submit a fixed price for that defined work.

T&M approach: If the extent of deck deterioration is still unknown and additional areas may be discovered as demolition continues, the parties may authorize the investigation and repair on T&M terms, potentially with an NTE amount and daily documentation.

The better pricing method is therefore determined by the level of certainty—not simply by contractor preference.

16. Bottom Line

A lump-sum change order provides one agreed price for a clearly defined change and gives the owner greater cost certainty. A time-and-materials change order bases payment on actual labor, materials, equipment, and other authorized costs, making it more flexible when the scope cannot be accurately determined in advance.

For commercial roofing, use lump-sum pricing when the work can be measured and priced reliably. Use T&M when concealed conditions, emergency work, investigation, or uncertain quantities make a reliable fixed price impractical. In either case, clearly document the scope, authorization, pricing basis, markup, schedule impact, and supporting records.

Related Questions

Sources

Last reviewed: October 2026

Related Resources

Commercial Roof Change Orders

Need Commercial Roofing Help?

ShieldLine Roofing can help commercial owners and general contractors evaluate roofing change-order scopes, document additional work, and establish clear pricing and approval procedures for commercial roofing projects.

Disclaimer: This information is provided for general educational purposes and is not legal, contractual, insurance, engineering, or construction-management advice. Change-order rights, pricing methods, markups, notice requirements, and authorization procedures depend on the governing contract and applicable law. Consult the contract and appropriate construction professionals before proceeding.

Commercial Roof Maintenance Programs

Rylee Hage - Founder of Shieldline Roofing

Meet the Founder: Rylee Hage

  • • Over 15 years of mastery in the roofing industry, bridging the gap between standard service and meticulous craftsmanship.
  • • Founded Shieldline Roofing on the principles of unwavering integrity and a profound commitment to protecting families.
  • • Dedicated to providing a personalized client experience built on a foundation of absolute trust.