What documentation should accompany every change order request?

Direct Answer

Every commercial roofing change order request should be supported by documentation that clearly shows what changed, why the change is necessary, how it affects the contract scope, the detailed cost impact, and any effect on the project schedule. A complete request should normally include the original contract requirement, drawings or specifications involved, field documentation, a detailed cost breakdown, schedule impact, subcontractor quotations when applicable, and the proposed change-order form or supporting correspondence.

The objective is to give the owner, general contractor, architect, construction manager, or other approving party enough information to determine whether the requested additional cost or time is justified. AIA guidance emphasizes that change-order documentation should clearly explain the change and that contract procedures should establish how changes are prepared and approved.

Who This Applies To

  • Commercial property owners
  • Developers and owner’s representatives
  • General contractors and construction managers
  • Commercial roofing subcontractors
  • Architects and design professionals
  • Facility and project managers
  • Construction administrators
  • Commercial roofing vendors submitting additional-work requests

Not for: This guidance addresses documentation for commercial construction and roofing change-order requests. The governing construction contract always controls the required notice, format, approval process, pricing requirements, and submission deadlines.

1. Start With the Original Contract Requirement

The change-order request should identify what the original contract required and explain how the proposed work differs.

Include:

  • Contract or purchase-order number
  • Relevant drawing number and revision
  • Specification section
  • Original scope of work
  • Applicable bid item or schedule-of-values line
  • Relevant contract language
  • Existing approved submittals where applicable

This establishes a baseline for determining whether the requested work is actually outside the original scope.

2. Clearly Describe the Reason for the Change

The request should state why the change is being proposed rather than simply saying that “additional work is required.”

Common reasons include:

  • Owner-requested scope change
  • Design revision
  • RFI response
  • Unforeseen existing condition
  • Conflicting drawings or specifications
  • Material substitution
  • Authority or code requirement
  • Site condition discovered during construction
  • Coordination issue with another trade
  • Manufacturer requirement

ConsensusDocs guidance recommends that contractor- or subcontractor-initiated change proposals identify the reason for the change, reference the relevant plans and specifications, explain the benefit to the owner or project, and identify the effect on project sequencing.

3. Include the Supporting Drawings and Specifications

If the change results from revised design information, the request should include the documents that demonstrate the revision.

Depending on the situation, this may include:

  • Revised architectural drawings
  • Revised roofing plans
  • Detail drawings
  • Specification revisions
  • Addenda
  • Bulletins
  • Architect’s supplemental instructions
  • RFI and response
  • Manufacturer details
  • Approved submittals

AIA construction-administration guidance recognizes RFIs as a primary mechanism for resolving questions during construction and notes that a clarification that changes contract scope or schedule requires the appropriate contract modification.

4. Provide Field Documentation

When the change results from an existing or unexpected field condition, photographs and site records can be particularly important.

Include:

  • Dated photographs
  • Location of the condition
  • Roof area or building elevation
  • Field measurements
  • Inspection notes
  • Marked-up drawings
  • Site observation reports
  • Relevant meeting minutes
  • RFI documentation
  • Records of previous communications

For example, if a roofing contractor discovers deteriorated decking after membrane removal, the change-order package should document the actual condition before replacement rather than simply stating that additional decking is required.

5. Show Exactly What Is Being Added or Deleted

The request should clearly distinguish between the original scope and the proposed revised scope.

Documentation Purpose
Original scope Establishes what was already included
Proposed additional work Defines what is being added
Deleted work Identifies credits or scope reductions
Substitution Shows what is replacing the original requirement
Net change Shows the final contract adjustment

A precise scope description reduces the possibility of later disagreement about what the approved change actually covered.

6. Include a Detailed Cost Breakdown

The change-order request should not present only a single unexplained lump-sum number when the contract or project procedure requires supporting detail.

Depending on the contract, provide:

  • Labor hours and rates
  • Material quantities and unit costs
  • Equipment costs
  • Subcontractor quotations
  • Delivery or freight costs
  • Disposal costs
  • Permitting costs
  • Applicable markups
  • Overhead and profit
  • Credits for deleted work
  • Net change-order amount

ConsensusDocs notes that change-order requests should provide enough detail concerning contract price and time for the parties to properly evaluate the proposed change.

7. Attach Subcontractor and Vendor Quotations

If the change involves another subcontractor, supplier, manufacturer, or specialty trade, include the supporting quotation when appropriate.

For a commercial roofing change, this might include:

  • Roofing material quotation
  • Sheet-metal fabrication quotation
  • Insulation pricing
  • Deck replacement pricing
  • Crane or equipment costs
  • Additional labor pricing
  • Manufacturer-required materials
  • Specialty testing costs

The quotation should correspond to the scope described in the change-order request.

8. Document the Schedule Impact

A change-order request should identify whether the additional work affects the construction schedule.

Document:

  • Number of additional calendar or working days requested
  • Reason for the delay
  • Activities affected
  • Relationship to the project critical path when applicable
  • Required resequencing
  • Additional mobilization
  • Overtime or acceleration requirements
  • Effect on subsequent trades
  • Updated schedule information

ConsensusDocs recommends that change proposals address the effect on contract time and price, while its guidance on delay documentation emphasizes revised schedules and supporting records when additional time is requested.

9. Include the RFI or Written Direction That Triggered the Change

If the change originated from an RFI, field instruction, design clarification, owner request, or other written direction, attach it to the request.

This creates a clear chain:

  1. Issue identified
  2. Question or request submitted
  3. Direction issued
  4. Scope impact identified
  5. Cost calculated
  6. Schedule impact calculated
  7. Change submitted for approval

AIA documentation guidance emphasizes maintaining written records of important decisions, communications, RFIs, work-change documents, approvals, and related project records.

10. Identify the Affected Contract Documents

The change-order request should identify exactly which documents are affected.

For example:

  • Drawing A5.01, Revision 3
  • Roof Plan R1.2
  • Specification Section 07 54 00
  • RFI-127
  • ASI-08
  • Approved roofing submittal
  • Manufacturer detail RD-14

This makes the request easier for the reviewing party to verify against the project record.

11. Document Any Material or Product Change

If the change involves a different roofing material or assembly, explain why the substitution is necessary and provide the supporting technical information.

Depending on the project, this may include:

  • Product data
  • Technical data sheets
  • Manufacturer letters
  • Warranty implications
  • Product approvals
  • Fire-performance information
  • Wind-uplift information
  • Compatibility information
  • Revised details

This is especially important when a material change could affect the roof system’s performance, warranty, code compliance, or approved design.

12. Explain Any Impact on Warranties

If the proposed change affects a manufacturer or workmanship warranty, document the potential impact before proceeding.

For commercial roofing, the request may need to address:

  • Manufacturer approval
  • Warranty inspection requirements
  • Changes to approved assemblies
  • Additional warranty costs
  • Modified warranty coverage
  • Coordination with the roofing manufacturer

Do not assume that a field-approved change automatically preserves the manufacturer’s warranty. The applicable manufacturer requirements should be confirmed before the work proceeds.

13. Include Required Notices and Submission Dates

Change-order procedures frequently include contractual deadlines for notifying the owner or construction manager.

The documentation should identify:

  • Date the condition was discovered
  • Date notice was provided
  • Date the change was priced
  • Date the formal request was submitted
  • Contractual notice requirement
  • Response deadline

Timely submission matters because accumulating change requests until the end of a project can make cost and schedule disputes more difficult to resolve. ConsensusDocs specifically recommends following the contract’s timing requirements for change-order submissions.

14. Include the Proposed Change-Order Form

The supporting documents should accompany the project’s formal change-order or proposed-change-order form when one is required.

The form should generally identify:

  • Project name
  • Change-order number
  • Date
  • Contractor
  • Subcontractor, if applicable
  • Description of change
  • Contract amount before change
  • Change amount
  • Revised contract amount
  • Contract time adjustment
  • Approval signatures

ConsensusDocs identifies its change-order form as a standardized method for documenting and formalizing adjustments to project scope, schedule, and contract price.

15. Keep the Approval Record

The documentation should not stop when the request is submitted.

Keep the final record showing:

  • Submitted request
  • Review comments
  • Revised pricing
  • Owner approval or rejection
  • Architect or design-professional review when applicable
  • Contractor approval
  • Subcontractor confirmation
  • Final executed change order
  • Updated contract value
  • Updated schedule

AIA notes that the parties to the construction agreement are responsible for approving changes to contract price or time, subject to the authority established by the contract.

16. Maintain a Change-Order Log

Every approved, pending, rejected, and withdrawn change should be tracked in a centralized change-order log.

Useful fields include:

  • Change-order number
  • Date submitted
  • Originator
  • Reason
  • Cost impact
  • Schedule impact
  • Status
  • Approval date
  • Related RFI
  • Related drawing revision
  • Related subcontractor proposal

AIA identifies change orders as a distinct construction-administration record alongside RFIs, supplemental instructions, applications for payment, and project record documents.

17. A Commercial Roofing Change-Order Documentation Checklist

Document Include When Applicable?
Change-order form Yes
Reason for change Yes
Original contract scope Yes
Relevant drawings/specifications Yes
RFI or written direction When applicable
Field photographs When condition-based
Marked-up drawings When applicable
Detailed cost breakdown Yes when required by contract/procedure
Subcontractor/vendor quotations When applicable
Material/product information When applicable
Schedule impact When applicable
Updated schedule When time is affected
Warranty impact When applicable
Approvals/signatures Yes

Bottom Line

Every commercial roofing change-order request should create a clear record of what changed, why it changed, what it costs, how it affects the schedule, and who authorized it. The strongest documentation connects the original contract requirement to the new condition or instruction, supports the scope with drawings or field evidence, provides a defensible cost breakdown, documents schedule consequences, and preserves the final approval.

There is no universal documentation package that overrides the project’s contract. The governing agreement and project procedures should determine notice periods, pricing requirements, approval authority, and required forms. AIA and ConsensusDocs guidance both emphasize documented procedures, supporting cost and schedule information, and timely processing of changes.

Related Questions

Sources

Last reviewed: October 23, 2026

Related Resources

What roofing closeout documents should a GC collect before turnover?

Need Commercial Roofing Help?

ShieldLine Roofing can help commercial project teams document roofing scope, field conditions, material changes, additional work, and project records so that proposed changes can be clearly evaluated and tracked.

Disclaimer: This information is for general educational purposes and does not constitute legal, contractual, engineering, or construction-management advice. The project contract and applicable specifications control the required change-order procedure, notice periods, documentation, pricing, and approval requirements.

New Construction Commercial Roofing

Rylee Hage - Founder of Shieldline Roofing

Meet the Founder: Rylee Hage

  • • Over 15 years of mastery in the roofing industry, bridging the gap between standard service and meticulous craftsmanship.
  • • Founded Shieldline Roofing on the principles of unwavering integrity and a profound commitment to protecting families.
  • • Dedicated to providing a personalized client experience built on a foundation of absolute trust.