Direct Answer
A force majeure clause is a contract provision that addresses extraordinary events outside a party’s reasonable control that prevent or materially delay contractual performance. For a Florida commercial roofing or construction contract, the clause should specifically address hurricanes, tropical storms, named storms, storm surge, flooding, high winds, mandatory evacuations, government emergency orders, and related supply or access disruptions rather than relying only on a generic reference to “acts of God.”
The clause should clearly explain what events qualify, what obligations are affected, what notice must be given, how schedule extensions are calculated, what happens to additional costs, what mitigation duties remain, and when either party can terminate the affected portion of the contract.
A Florida Bar model agreement, for example, expressly includes hurricanes within its force majeure provision and ties relief to circumstances beyond the parties’ control that cannot be overcome through reasonable diligence without unusual expense. Florida contract guidance also emphasizes that contract provisions should be read as part of the agreement as a whole, making clarity and consistency between the force majeure clause and other delay provisions important.
Who This Applies To
- Commercial property owners
- General contractors
- Commercial roofing contractors
- Developers
- Property managers
- Construction managers
- Subcontractors
- Owners’ representatives
Not for: This is general contract-drafting information, not legal advice. A Florida construction attorney should review the final clause before it is incorporated into a binding contract.
1. Specifically Name Hurricanes and Tropical Storms
Do not rely exclusively on broad wording such as “acts of God.” Hurricanes should be expressly identified as qualifying events.
A well-drafted clause can address:
- Hurricanes
- Tropical storms
- Tropical depressions
- Named storms
- Extreme wind events
- Storm surge
- Flooding
- Hurricane-related rainfall
- Mandatory evacuations
- Government emergency orders
This reduces uncertainty about whether a particular storm falls within the agreed definition.
2. Define the Actual Effect on Performance
A hurricane should not automatically excuse every contractual obligation merely because a storm occurs.
The clause should connect the event to an actual inability or material delay in performance.
For example, qualifying effects could include:
- Unsafe site conditions
- Government-mandated closure
- Evacuation orders
- Restricted access to the property
- Damage to the project or existing roof
- Road closures
- Loss of electricity or essential utilities
- Material delivery interruption
- Supplier shutdowns
- Labor availability disruptions
- Crane or equipment unavailability
The key is to establish a causal connection between the hurricane and the affected contractual performance.
3. Separate Schedule Relief From Monetary Relief
This is one of the most important drafting points.
A force majeure provision should state whether the event provides:
- Additional contract time
- Compensation for additional costs
- Both time and cost relief
- Time relief only
- Another specifically negotiated remedy
Do not assume that an extension of time automatically means the contractor is entitled to additional compensation.
Florida construction contracts commonly distinguish between schedule extensions and monetary damages. Florida Bar materials discuss “no damages for delay” provisions and note that such clauses can limit a contractor’s remedy to an extension of time depending on the contract language and circumstances.
4. Establish a Notice Requirement
The contract should establish how quickly a party must notify the other party after a hurricane begins affecting performance.
The clause should specify:
- Who must provide notice
- Who must receive notice
- Required delivery method
- Required timing
- Information that must be included
- Whether continuing updates are required
The notice should identify the affected work, expected impact, anticipated duration, and known consequences where reasonably available.
5. Require Documentation of the Delay
A hurricane clause should not make delay documentation optional.
Require the affected party to maintain appropriate records such as:
- Official storm notices
- Evacuation orders
- Site-closure notices
- Weather records
- Photographs
- Delivery records
- Supplier correspondence
- Labor availability records
- Daily reports
- Updated project schedules
This helps establish whether the storm actually affected the critical work rather than simply occurring somewhere in the region.
6. Address Site Access and Evacuation
For Florida roofing projects, site access can become a major issue after a hurricane.
The clause should address situations where:
- The property is evacuated
- Local authorities prohibit access
- The building is unsafe
- The owner temporarily closes the property
- Roof access is prohibited
- Roads are inaccessible
- Emergency operations take priority over construction
These conditions should be treated separately from ordinary weather delays when appropriate.
7. Address Material and Equipment Delays
Hurricane impacts can continue after the storm itself has passed.
For example, a roofing contractor may be unable to obtain:
- Membrane
- Insulation
- Fasteners
- Sheet metal
- Adhesives
- Replacement equipment
- Crane services
- Temporary protection materials
A properly written clause should explain when a supply-chain disruption qualifies as a force majeure consequence and what evidence must be provided.
8. Include a Duty to Mitigate
The party relying on force majeure should generally be required to take reasonable steps to minimize the impact.
For a roofing project, that could include:
- Securing exposed materials
- Protecting temporary roof conditions
- Installing temporary weather protection where appropriate
- Re-sequencing unaffected work
- Obtaining reasonably available alternative materials
- Communicating schedule changes promptly
Florida contract principles recognize the importance of reasonable efforts to avoid preventable losses. Florida Bar materials discussing avoidable consequences explain that losses that could reasonably have been avoided without undue burden may affect recovery.
9. Address Emergency Roof Protection
For commercial roofing contracts, the clause should make clear that force majeure does not eliminate reasonable emergency responsibilities.
For example, after a hurricane, the contractor may still be required to take reasonable steps to:
- Secure loose materials
- Protect temporary roof openings
- Prevent avoidable water intrusion
- Notify the owner of emergency conditions
- Document storm-related damage
The clause can distinguish between emergency protective measures and the contractor’s normal contractual scope.
10. Address Pre-Existing Conditions
The contract should distinguish hurricane damage from conditions that existed before the storm.
For example, if a roof already had:
- Open seams
- Deteriorated flashings
- Existing leaks
- Damaged membrane
- Deferred maintenance
the parties should have a method for determining whether subsequent damage was caused by the hurricane or resulted from an existing condition.
11. Explain How Schedule Extensions Are Calculated
A strong clause should define how much additional time is available.
It may provide an extension corresponding to the period during which the qualifying event actually prevents or materially delays performance, together with additional reasonable time required to remobilize and resume work.
Avoid vague language such as “the contractor will receive additional time for hurricane delays” without explaining how the extension is established.
12. Address Multiple Hurricanes
Florida projects may encounter more than one qualifying storm during a project.
The clause should apply separately to each qualifying event rather than assuming that one hurricane is the only possible event.
Each event should be documented separately where necessary, including:
- Date of event
- Site impact
- Work affected
- Duration
- Remobilization period
- Schedule impact
13. Address Termination for Extended Force Majeure
If a hurricane or related condition prevents performance for an extended period, the contract should establish when either party may terminate the affected portion of the agreement.
The clause should address:
- Minimum duration before termination rights arise
- Required written notice
- Payment for completed work
- Disposition of stored materials
- Removal of equipment
- Protection of unfinished work
- Closeout responsibilities
Some force majeure provisions use a defined continuation period before termination becomes available. A Florida Bar-hosted agreement, for example, uses a notice procedure and an extended-duration termination mechanism.
14. Coordinate the Clause With Other Contract Provisions
The force majeure clause should be reviewed together with:
- Schedule provisions
- Liquidated damages
- No-damage-for-delay provisions
- Change-order procedures
- Insurance requirements
- Notice provisions
- Emergency work provisions
- Termination provisions
- Risk-of-loss provisions
Otherwise, two provisions may appear to provide conflicting remedies.
Florida Bar contract guidance emphasizes interpreting contracts as a whole rather than isolating individual provisions.
15. Sample Hurricane Force Majeure Language
The following is a starting-point example for attorney review, not a substitute for legal drafting:
FORCE MAJEURE — HURRICANE AND SEVERE WEATHER EVENTS
Neither Party shall be liable for a delay in performing an obligation under
this Agreement to the extent that performance is materially prevented or
delayed by an event beyond the affected Party's reasonable control, including
a hurricane, tropical storm, named storm, storm surge, extraordinary
flooding, extreme wind event, mandatory evacuation, governmental emergency
order, or other extraordinary weather-related event (a "Force Majeure Event").
A Force Majeure Event shall provide relief only to the extent that it
materially prevents or delays the affected performance. The occurrence of a
hurricane or other storm in the geographic area, by itself, shall not
automatically excuse performance.
The affected Party shall provide written notice to the other Party within
[NUMBER] days after becoming aware that the Force Majeure Event is materially
affecting performance. The notice shall identify, to the extent reasonably
known, the affected work, anticipated duration, expected schedule impact,
and measures being taken to mitigate the delay.
The affected Party shall use reasonable diligence to mitigate the effects of
the Force Majeure Event, protect the Work from avoidable damage, and resume
performance as soon as reasonably practicable.
Where the Force Majeure Event affects the Contractor's performance, the
Contractor shall be entitled to a reasonable extension of the Contract Time
to the extent the critical path is actually delayed, including reasonable
time required for safe remobilization and resumption of Work.
Additional compensation resulting from a Force Majeure Event shall be
available only to the extent expressly provided elsewhere in this Agreement
or approved through a written Change Order.
The Contractor shall maintain reasonable documentation supporting the
claimed delay, including applicable governmental orders, site conditions,
delivery records, photographs, project schedules, and other records
reasonably necessary to establish the effect of the Force Majeure Event.
If a Force Majeure Event continues for more than [NUMBER] consecutive days
and materially prevents performance of a substantial portion of the Work,
either Party may terminate the affected portion of this Agreement upon
written notice, subject to payment for Work properly performed and other
surviving contractual obligations.
Nothing in this provision relieves either Party from obligations that can
reasonably be performed despite the Force Majeure Event or from taking
reasonable measures to prevent avoidable damage or loss.
16. Why Specific Hurricane Language Matters
For a Florida commercial roofing contract, specificity is valuable because hurricane impacts can range from a short site closure to widespread property damage, evacuation, material shortages, utility interruption, and prolonged remobilization.
A generic clause may leave important questions unanswered. A stronger clause establishes the parties’ expectations before the storm occurs.
Bottom Line
A hurricane force majeure clause should do more than say that hurricanes are “acts of God.” It should define qualifying events, require a material impact on performance, establish notice and documentation requirements, provide a clear method for schedule relief, explain whether additional costs are recoverable, require reasonable mitigation, address emergency protection and remobilization, and establish termination rights for prolonged events.
For a Florida commercial roofing or construction contract, the final language should be reviewed by a Florida construction attorney because the enforceability and interaction of force majeure, delay, damages, insurance, and other contractual provisions depend on the complete agreement and the circumstances of the project.
Related Questions
- How are night and weekend work schedules coordinated with building operations?
- What response times should a commercial roof maintenance contract guarantee?
- What should happen during the first hour of an emergency commercial roof leak?
Sources
- The Florida Bar — Contract and Construction Law Resources
- The Florida Bar — Construction Delay and No-Damage-for-Delay Clauses
- The Florida Bar — Sample Interagency Agreement with Force Majeure Provision
- The Florida Bar — Statutes Affecting Florida Construction
- The Florida Bar — Construction Contract Guidance
Last reviewed: October 2026
Related Resources
How Are Night and Weekend Work Schedules Coordinated With Building Operations?
Need Commercial Roofing Help?
ShieldLine Roofing can help commercial property owners, facility teams, developers, and contractors plan roofing work around Florida weather risks, emergency response requirements, and project scheduling considerations.
Disclaimer: This information is provided for general educational purposes and is not legal, insurance, engineering, underwriting, or contract-drafting advice. A qualified Florida construction attorney should review any force majeure clause before it is incorporated into a contract.