Direct Answer
A property owner in Florida can obtain a lien release from a roofing contractor by requesting a properly completed written waiver and release of lien in exchange for a progress payment or final payment. The release should identify the property, the payment, and the labor, services, or materials covered. Florida Statutes Section 713.20 provides statutory forms for progress-payment and final-payment releases.
For stronger protection, the owner should also verify that roofing subcontractors and material suppliers have been paid, obtain appropriate releases from those parties, and request the contractor’s final payment affidavit when required. A release from the general roofing contractor alone does not necessarily eliminate lien exposure from unpaid subcontractors or suppliers.
Who This Applies To
- Commercial property owners paying for roof repairs, restoration, or replacement.
- Facility managers overseeing roofing contractors and subcontractors.
- Property developers and general contractors administering construction payments.
- Owners who have received a Notice to Owner from a roofing subcontractor or supplier.
1. Request the Correct Type of Lien Release
The appropriate release depends on the payment stage and the work being covered.
| Release type | When to use it | What it generally covers |
|---|---|---|
| Progress-payment waiver and release | When paying an interim roofing invoice or progress draw. | Labor, services, or materials furnished through the specified date. Retainage and later work are excluded as stated in the statutory form. |
| Final-payment waiver and release | When making the final payment for the covered work. | The lien rights for labor, services, or materials furnished within the scope of the release. |
| Recorded lien satisfaction or release | When a claim of lien has already been recorded against the property. | The formal discharge of the recorded lien through an applicable statutory method. |
Florida Statutes Section 713.20(4) and (5) sets out forms for progress-payment and final-payment releases. Section 713.21 addresses methods for discharging a perfected lien. These documents serve related but different purposes.
2. Match the Release to the Payment
Before releasing funds, the owner should confirm that the document accurately identifies the roofing contractor, property, payment amount, and applicable work period. The owner should also check whether the release excludes retainage, unpaid change orders, disputed amounts, or work performed after the stated date.
For a progress payment, Florida law allows the lienor to condition a release delivered in exchange for a check on the check actually clearing. Owners should coordinate the release and payment so the document does not unintentionally waive rights beyond the payment being made.
3. Collect Releases from Subcontractors and Suppliers
A commercial roofing contractor may hire subcontractors and purchase materials from suppliers. If those parties remain unpaid, they may have potential lien rights even if the property owner has already paid the main contractor.
To reduce this risk, the owner should:
- Review Notices to Owner received from roofing subcontractors and material suppliers.
- Request appropriate progress-payment or final-payment releases from parties entitled to provide them.
- Match supplier invoices, delivery records, subcontractor invoices, and releases to the relevant payment period.
- Review the contractor’s payment affidavit and investigate any outstanding amounts before making final payment.
- Where appropriate, obtain advice about direct payment to an unpaid lienor and deducting that amount from the contract balance under applicable law.
Florida Statutes Section 713.06 governs important owner-payment protections and the contractor’s final payment affidavit. The owner should not assume that a general contractor’s statement alone resolves every outstanding payment claim.
4. Obtain the Final Payment Affidavit
When required under Florida Statutes Section 713.06, the contractor must provide a final payment affidavit stating whether lienors under the direct contract who timely served a Notice to Owner have been paid in full. If some remain unpaid, the affidavit must identify them and the amounts due or to become due.
The owner should compare the affidavit with the Notices to Owner received, payment records, and releases collected. If the affidavit identifies outstanding balances, those amounts should be addressed before releasing the remaining contract funds.
5. What If a Lien Has Already Been Recorded?
If a roofing contractor has recorded a claim of lien, a routine progress-payment release may not be enough to clear the recorded public record. The owner should obtain an appropriate satisfaction or release of the recorded lien and confirm that it is properly acknowledged and recorded where required.
Under Florida Statutes Section 713.21, a lien may be discharged through specified methods, including a duly acknowledged and recorded satisfaction or release. The recorded document should identify the original lien by its official-records reference number and recording date as required by the statute.
6. Owner’s Lien-Release Checklist
- Confirm the identity of the contractor and the property covered by the release.
- Choose the appropriate progress-payment or final-payment form.
- Verify the amount paid and the period or work covered.
- Coordinate any conditional release with the actual payment clearing.
- Identify subcontractors and suppliers who served Notices to Owner.
- Collect and reconcile applicable releases and payment records.
- Obtain the contractor’s final payment affidavit when required.
- If a lien was recorded, verify that the lien is formally discharged and the release is recorded where necessary.
Bottom Line
A Florida property owner should obtain lien releases throughout a roofing project rather than waiting until a dispute arises. Progress-payment releases help document interim payments, while a final-payment release and the contractor’s final payment affidavit help close out the project. Owners should also address unpaid subcontractors and suppliers and ensure any already-recorded lien is properly discharged.
Florida Statutes Sections 713.20, 713.21, and 713.06 provide the principal statutory framework for releases, discharge of liens, and owner-payment procedures. For substantial commercial roofing contracts or disputed claims, consult a Florida construction attorney before making final payment or relying on a release.
Related Questions
- How does a Notice to Owner protect a roofing subcontractor or supplier?
- How do I file a commercial roof insurance claim in Florida?
- Who pays for the roof under a Florida NNN lease?
Sources
- Florida Statutes Section 713.20 (2026) — Waiver or release of liens
- Florida Statutes Section 713.21 (2026) — Discharge of lien
- Florida Statutes Section 713.06 (2026) — Liens of persons not in privity; proper payments
- Florida Department of Business and Professional Regulation — Florida’s Construction Lien Law guide
Last reviewed: October 2026
Related Resources
Learn how payment notices can affect construction lien rights in how a Notice to Owner protects a roofing subcontractor or supplier.
Need Commercial Roofing Help?
Good project documentation helps commercial property owners manage roofing work, payments, and closeout. Before authorizing major repairs or replacement, make sure the project scope and payment records are clearly documented.
Explore commercial roof replacement and re-roofing services.
This article provides general educational information about Florida construction lien procedures and is not legal advice. Requirements may depend on the contract, payment status, parties involved, and recorded documents. Confirm project-specific obligations with a qualified Florida construction attorney.